Hello Experts,
Please throw me some light on the below scenario. This is very urgent. Your valuable inputs will be appreciated.
My client's requirement is to create the Alternate Saturdays (2nd & 4th only) as holidays where I can not create the same using the Holiday Calendar since for the same location there are other work schedules also with 6 day week & 5 day weeks.
Hence I had decided to create the Period Work Schedules for all the 52 weeks by following the calendar but its not carrying forward correctly(By giving the same year as starting point) to the next year when generating it for next 4 years. Please help me in this regard urgently. Do we have a solution using the Period work schedules for this scenario? If yes, then how? or is it better going with selection rules etc..? Please help me.
Thanks in Advance,
M.V.V