G'Day All ,
We have a unique requirement from our client . Our client does the same preventive maintenance work every 3 weeks , 6 weeks and then 10 weeks .As this sequence is a legal requirement ( we cant change to 3 week , 6 week , 9 week )
Maintenance packages required for 3 week , 6 week , 10 week . Then 3 week , 6 week , 10 week as so on.
How can we achive this in SAP ? ( attaching a modified screen shot of what , I would like to achive )
Thanks & Cheers